Reconstruction of the Dane river embankment

Bastionu bridge





Project: A new bridge with lifting mechanism during the construction of the Dane and access arrangement Dane coast. Bastionų street construction (Stage. Bastionų g. Of Danes. To the Dane River and from the Dane River to Willow Street, Phase II. Bastionų g. Of Willow street to street Wave).


Description: The aim of the project - to build a raised 4-lane bridge with a footpath on both sides and bicycle path on one side. Equipped with rain water from the bridge deck and the water from the machinery space and the collection of rain water drainage networks with the initial water treatment of pollutants, installation of lighting. Construct 4 (four) lane street with the infrastructure, construction of pedestrian paths on both sides of the street and bike lanes on one side of the street.


The planned value of the project: 9,617,985.52 euros, of which the investment project - ~ 6,000 euros, a technical project - 753,134.25 euros, the project expertise - ~ 30,315.52 euros, project supervision - ~ 106,327.54, maintenance - ~ 60,631.04, contract work - ~ 8,661,577.17 euros.


Design: 2015-10-26 signed Bastionų str. with a new bridge over the River Dane design and project supervision services contracts. Designer - "Kelprojektas". Technical drafting period - 20 months.


Construction: 2018 March - 2020 July.


Project managers: Gintaras Dovidaitis e-mail.: Gintaras.dovidaitis@klaipeda.lt, phone. No. 8 46 39 61 08 and Edita Čerbienė (edita.cerbiene@klaipeda.lt).